China Refinery Maintian Schedule

China Refinery Maintian Schedule (updated on Jul 26)

PCs

Facility Shutdown

Capacity
(10,000mt/yr)

Shutdown Date

Regions
Tahe PC
Delayed Coking
120
May 25 –Jul 31
Xinjiang
Lanzhou PC
Coking
140
Mid Jul
Gansu
Maoming PC

Atmospheric and vacuum distillation

500
Aug
Guangdong
Catalytic cracking
90
Aug

Diesel hydrogenation

45
Nov
Jingmen PC

Catalytic cracking

80

Jun 16 – Jul 15

Hubei

Heavy oil catalytic cracking

120

Jul 20 – Sept 2

Qilu PC

Atmospheric and vacuum distillation

800
Oct, 2012
Shandong
Coking
140
Oct, 2012
Qingdao PC

Overall maintenance

500

Aug 20 – Oct 10

Hohhot Refinery

Shutdown
150

Aug 5, 2011 – Aug 8, 2012

Inner Mongolia

Jinling PC

Atmospheric and vacuum distillation

300

Early Jun – Early Jul

Jiangsu
Yangzi PC

Atmospheric and vacuum distillation

450

Jul 15 – mid Aug

Jiangsu
Liaohe PC

Catalytic cracking

80
Jul 1 – 25
Liaoning

Liaoyang PC

Atmospheric and vacuum distillation

550

Jul 20 – Aug 4

Liaoning

Delayed Coking

100

Jul 20 – Aug 4

Tianjin PC

Overall maintenance

1300

Aug 15 – late Sept

Tianjin
Wuhan PC

Overall maintenance

500

Jun 2 – Jul 20

Hubei
Shanghai PC

Atmospheric and vacuum distillation

600

Jun 8 – Jul 17

Shanghai
Coking
100

Jun 12 – Jul 11

Medium pressure hydrocracking

150

Jun 12 – Jul 26